The Michigan City Sanitary Board’s regular meeting on December 13, 2017 included several procurement and budget matters. The board approved a $500 contract for leaf disposal at the Hitchcock Street facility. It approved adding an IT programmer/application developer position, budgeted at up to $40,000 annually, and approved the salary resolution with the recruitment-and-retention provision removed for further review. The board also approved the 2018 safety consultant contract; no amount was stated. A clean-fleet procurement policy favoring low-emission and alternative-fuel vehicles and equipment was adopted, and the board authorized submission of a lead-testing grant application described as having no cost to the district or city. Six resolutions identifying funding sources for existing grants were approved.
For the Highway 12 project, staff recommended awarding the contract to D&M Excavating at an adjusted bid of approximately $634,452, but the board deferred action until its January 10 meeting to review available funds; the transcript notes the city had approved $500,000. For the Lakeland Triangle lift-station project, Woodruff & Sons was identified as the apparent low bidder at about $377,767, but the board likewise planned to consider the award at the January meeting. A $40,600 engineering proposal for Ohio Street sewer design and bid documents was presented, but the transcript does not capture a clear vote on it. The board also discussed ongoing sewer and facility projects and related funding, with no other clearly documented contract awards.
Source
Access LaPorte County Media