# High School Building Committee, Nov  19, 2026


**Body:** Nashoba Regional School Committee
**Date:** November 20, 2026
**Jurisdiction:** SLED

**Tags:** Construction & Infrastructure, Physical Infrastructure


The Nashoba Regional School District High School Building Committee met on November 19, 2026, to review the new high school project. The committee approved two furniture, fixtures, and equipment proposals totaling $2,628,315.32, covering supply, installation, and removal of packaging and waste. The proposals were presented as the complete furniture package for the building, with approximately $125,000 remaining in the FF&E budget for incidentals. Staff said the purchasing timeline was intended to allow purchase orders to be issued before anticipated price increases. The committee also approved the prior meeting minutes and received project updates; construction was reported on schedule, with permanent power connected November 6.

**Source:** Nashoba Regional School Committee