Meeting
Road Advisory Meeting 11/16
Body
Cass County, ND
Date
November 17, 2026
Jurisdiction
State & Local
Cass County Road Advisory meeting, November 17, 2026 (titled “Road Advisory Meeting 11/16”): County Engineer Kyle reported that 2026 road and bridge work finished about $5 million under budget, largely due to favorable bids and projects continuing over winter. The proposed 2027 construction program was estimated at roughly $50 million, including resurfacing, road grading and reconstruction, culvert work, and projects associated with the diversion. A major package of diversion-related county-road connections was expected to go out for bid in the coming month. The advisory body approved the 2027–2031 highway and bridge plan by motion and roll-call vote. The C31 Cheyenne Bridge project was awarded for about $6.5 million, substantially below the engineer’s estimate; KLJ is conducting construction inspection, and completion is scheduled for October 31, 2027.
The engineer also reported grant support for upcoming work: 100% of construction costs for the C31 bridge, 80% for a Raymond Township bridge, $900,000 in Transportation Alternatives funding toward a roughly $1.1 million shared-use path project, and a $240,000 award toward a $300,000 speed-display-sign project, currently scheduled for 2030. The board received and filed a long-range west-perimeter-road study; no construction decision or procurement approval resulted. Members discussed seeking state highway funding to address road impacts from a planned energy park. The advisory body also approved an engine-brake ordinance proposal for referral to the County Commission’s formal reading and adoption process. Load-pass permits had generated about $272,000 since the system was introduced, with a revised fee schedule anticipated for January 1.
Source
Cass County, ND