GJPS BOE Finance and Facilities Committee Meeting - 11-17-26
Body
Zoom Account
Date
November 16, 2026
Jurisdiction
State & Local
The Gahanna-Jefferson Public Schools Board of Education Finance and Facilities Committee met November 17, 2026. The facilities update reported that the high school parking lot was complete and final occupancy had been approved; remaining signage, wayfinding, and temporary traffic-signal work was scheduled, with larger off-site road improvements planned for next summer. High school change orders were 2.7% of project volume, with about $12,000 in change orders this month and a projected closeout near 3.2%. Middle School West and South construction was progressing, with work continuing toward winter enclosure. The financial report showed the high school project 97% paid, with pay applications expected to close near year-end; mechanical and preschool work were also approaching closeout. No contract awards, bids, or vendor selections were made.