⚡ Energy & Utilities 🏗️ Construction & Infrastructure Physical Infrastructure Grants & Funding

The West Memphis Utility Commission met November 16, 2026. The commission approved the October minutes and adopted a ratepayer-protection pledge for large data-center customers, requiring them to fund infrastructure built to serve their facilities. Staff described existing cost-of-construction agreements and task orders for Google, including 13 active orders, with customers paying before construction begins. The commission also approved a recommended bid from Gaines Williams and Associates; the transcript does not clearly identify the bid’s scope. Staff reported that roughly $1 million in vehicle purchases—including a water-department standby truck and vehicles for other departments—was accelerated after additional ARPA reimbursement became available. A separate RFP for regulatory counsel received one response, and staff requested approval to engage the firm; the transcript does not clearly capture the outcome of that request.

Staff reviewed the replacement combined-cycle natural-gas plant at Independence in Newark, Arkansas, which is intended to replace generation from coal units scheduled to close in 2028 and 2030. West Memphis has spent a little over $7 million of its $20 million first bond issue on its share of the project and expects to issue roughly $25 million in additional bonds around the third quarter of 2027. Staff also reported that the new SpryPoint cloud-based customer information system went live in early November, discussed customer concerns over payment-processing fees, and noted that the utility’s rate study is awaiting audited financial statements. October service revenue was $3.3 million and expenses were $4.8 million; year-to-date net profit was reported at $1.8 million.

Source

City of West Memphis