Killam School Building Committee 11-16-2026

Body

RCTV Studios

Date

November 15, 2026

Jurisdiction

State & Local

🏗️ Construction & Infrastructure Physical Infrastructure

The Killam School Building Committee met on November 16, 2026, for a construction update, budget and schedule review, procurement approvals, and discussion of HVAC issues. Site work continued with unsuitable soil removal and installation of footings; foundation work was expected to continue across the site, with a crane and initial steel delivery anticipated after Thanksgiving. The committee reviewed the MSBA budget revision, including an approved construction budget of $76,681,000 and a total project budget of approximately $130 million. The project team reported $3.6 million expended to date and discussed upcoming furniture and technology allocations. The schedule review identified substantial completion in mid-December and later occupancy and Phase 2 milestones.

The committee unanimously approved Change Order No. 1 for $29,450.39, covering asbestos-related work through a lump-sum arrangement. Discussion weighed potential savings from a credit against the schedule benefit of avoiding work stoppages; members also raised questions about whether the estimated quantities set an upper limit on costs, with follow-up verification from the hazardous-materials consultant noted. The committee approved payment of submitted project invoices, including Bright Builders’ requisition for about $1.17 million, an LBA invoice for $164,324.22, Bid Docs Online for $4,500, and UTS for $2,577.50. Following executive session on potential litigation involving MB Kenny and unresolved HVAC issues, the committee voted to authorize a team to negotiate with the relevant parties to resolve those issues.

Source

RCTV Studios