Award
Santa Barbara County SCON-005724 : BC24152 862417 Coastal Access IMP Const LP
SCON-001556 BC24152 862417 Coastal Access Improvement Via Real Summerland - updating to new encumbered contract. Prog...
Recipient
TAYLOR JANE CONSTRUCTION LP
Award Amount
$1,242,284.10
Ceiling
$1,242,284.10
Awarded
September 10, 2024
Period of Performance
Sep 10, 2024 – Dec 31, 2026
Identifier
SCON-005724 : BC24152 862417 Coastal Access IMP Const LP
Santa Barbara County Public Works awarded an encumbered construction contract to TAYLOR JANE CONSTRUCTION LP for the Coastal Access Improvement project at Via Real in Summerland. The five lines comprise $1,177,682.94 for the project, $30,000.00 added back under CCO06, $4,901.00 for CCO03 changes and restoration of disturbed landscape areas, $5,433.23 for CCO08/09/12 (with CCO15 listed without an amount), and $24,266.93 for CCO16/17/18. The listed line amounts total $1,242,284.10, matching the stated award amount. The source identifies a Board Contract (Encumbered), with contract dates of September 10, 2024 through December 31, 2026. No quantities or separate OEMs are identified.
Description
SCON-001556 BC24152 862417 Coastal Access Improvement Via Real Summerland - updating to new encumbered contract. Prog 2830 - 100%