Award

Greenville 26-4009

City Wide Bridge Maintenance

Recipient

Saluda Construction, LLC

Award Amount

$1,596,315.00

Ceiling

$1,596,315.00

Awarded

September 15, 2026

Identifier

26-4009

The City of Greenville awarded a contract to Saluda Construction, LLC for city-wide bridge maintenance repairs following Hurricane Helene damage, covering various structural repairs and replacements with a contract period from June to July 2026.

Description

The City of Greenville awarded the contract for the City-Wide Bridge Maintenance Project involving repairs on city-owned bridges damaged by Hurricane Helene in 2024. The scope includes traffic control, erosion repair, masonry grout repair, mortar joint repairs, slope protection, railing and guardrail replacement, timber pile repairs, and utility pipe repairs. The contract duration is from June 18, 2026, to July 21, 2026.