Award

Utah U3P #DA20060

DFCM Construction-Pre Qualified Mechanical-UVU Computer Science Bldg. Chillers 6/7 Replmnt-20280790

Recipient

Mechanical Service & Systems, Inc.

Award Amount

$880,852.00

Ceiling

$880,852.00

Awarded

January 07, 2021

Identifier

DA20060

The State of Utah, through the Division of Facilities Construction and Management (DFCM), awarded Mechanical Service & Systems, Inc. a contract for the replacement of two chillers (Chillers #6 & #7) and associated chilled water pumps at Utah Valley University in Orem, Utah. The project includes an additive alternate for replacing condenser water pumps. The contract covers all work and materials as specified in the plans and specifications, with a construction cost estimate of approximately $1,000,000. The project involves mechanical services, including the removal and replacement of chillers and pumps, and is to be submitted for energy incentives. Notable contract requirements include builder's risk insurance, general liability, bid bonds, subcontractor lists, liquidated damages, and adherence to project completion deadlines. The contract was awarded to Mechanical Service & Systems, Inc., with a total obligated amount of $880,852. The project is located in Orem, Utah, and the award is under the jurisdiction of Utah (US-UT). The primary contact for the project is Guy Wayman, whose email is gwayman@utah.gov. The award includes line items for the base bid and an additive alternate, with detailed bid tabulations available. The award was posted as an invitation for bid, with a response deadline of June 8, 2020.

Description

This project includes the replacement of two existing chillers (Chillers #6 & #7) and the associated chilled water pumps. The condenser water pumps shall be replaced per add ALT #1. This project shall be submitted for energy incentive programs through KW Engineering. The base bid shall include all work and materials associated with the project as outlined in the plans and specs.

View original record