Award
Snohomish County Purchasing Division PW-24-0355SB
Elliott Road Flood Reduction
Recipient
Marshbank Construction
Award Amount
$5,349,063.00
Ceiling
$5,349,063.00
Awarded
March 05, 2025
Identifier
PW-24-0355SB
Snohomish County awarded a contract for the Elliott Road Flood Reduction project involving bridge construction, road raising, creek realignment, and habitat improvements with work scheduled for summers 2025 and 2026.
Description
This contract involves the improvement of Elliott Road by constructing a bridge, raising the roadway, re-aligning Anderson Creek, and other related work, in accordance with the attached plans, contract provisions, and the 2025 WSDOT Standard Specifications. The project includes two in-water work windows during summer 2025 and summer 2026. Work is divided into two groups: Group 1: Construction of the bridge, road improvements, and temporary bypass road. Group 2: Re-aligning Anderson Creek and improving fish habitat.