# Santa Barbara County 7193

Geotechnical investigations and report for the new SB Probation Headquarters project. Proj. # 19014 - Change order to...

**Recipient:** GEOSOLUTIONS INC

**Award Amount:** $38,285.00
**Ceiling:** $38,285.00

**Awarded:** January 30, 2024

**Identifier:** 7193

Santa Barbara County awarded GEOSOLUTIONS INC a $38,285 purchase order (PO 7193; project 19014) for geotechnical and material testing services for the new Santa Barbara Probation Headquarters. The single listed line item is quantity 1: geotechnical investigations and report, including added geotechnical plan review, grading observation, density testing of compacted fills, footing excavation inspection, and associated laboratory testing to determine maximum density under ASTM D1557. This change order extends the contract duration to January 31, 2027. No other OEMs or vendors are mentioned.

### Description

Geotechnical investigations and report for the new SB Probation Headquarters project. Proj. # 19014 - Change order to incorporate additional scope of work to provide Geotechnical plan review, Grading observation, Density testing of compacted fills, Inspection of footing excavations, and Associated laboratory testing including determination of maximum density (ASTM D1557). Extend the contract duration to 1/31/27.