Award
Utah U3P #MW22039
DFCM Construction-SLCC RRC LAC Arena Seating/Gym Floor Replacement-22057660
Recipient
Croft Beck Floors Incorporated
Award Amount
$162,908.00
Ceiling
$162,908.00
Awarded
January 27, 2022
Identifier
MW22039
Award for arena seating and gym floor replacement at SLCC RRC LAC, awarded to Croft Beck Floors Incorporated for $162,908. The project includes replacing and painting the gym floor with a completion date of May 27, 2022.
Description
Project involves arena seating and gym floor replacement at SLCC RRC Lifetime Activity Center (LAC), Salt Lake Community College - Redwood Road Campus, Taylorsville, Utah. The project includes replacing and painting the gym floor. The bid was an Invitation for Bid (IFB) with a construction cost estimate of $160,000. The awarded contractor is Croft Beck Floors Incorporated with a total bid amount of $162,908.00. Completion date is May 27, 2022, with liquidated damages of $1,000.