Award

Guilford County NC MUNIS #20139

CMAR for Sheriff's Office Building

Recipient

Frank L. Blum Construction / W.C. Construction

Award Amount

$92,430.00

Ceiling

$92,430.00

Awarded

September 25, 2023

Identifier

20139

The award includes multiple contracts for the Guilford County Sheriff's Office Building project in Greensboro, NC. The Guilford County Purchasing Department awarded a construction management at risk (CMAR) contract to Frank L. Blum Construction / W.C. Construction with an obligated amount of $92,430 for pre-construction services. The Guilford County Purchasing Department also awarded a separate construction management services contract for the new Sheriff's Office building, with an estimated total project budget of $18 million, including demolition of old structures, construction of a new approximately 40,000 sq ft two-story building, and a surface parking lot with about 145 spaces. The project is scheduled to start in October 2023, with substantial completion expected by December 2024. The contracts emphasize MWBE participation, detailed scope of preconstruction and construction services, and compliance with North Carolina statutes. The project involves design by Walter Robbs Callahan & Pierce Architects, with various engineering consultants involved. The awards include detailed contractual provisions, insurance, bonds, and project milestones.

Description

Construction Manager at Risk for the completion of the Law Enforcement Administration (LE Admin) Building project including demolition of old jail, construction of new two-story building approx. 40,000 sq ft with basement storage and parking, demolition of existing Sheriff's Administrative Office Building, and construction of surface parking lot with approx. 145 spaces.

View original record