Award
The University of New Mexico RFP-2645-27
UNM Construction Manager at Risk (CMAR) Phase 1 of University Stadium Improvements
Recipient
Jaynes Corporation
Award Amount
$2,225,406.00
Ceiling
$2,225,406.00
Awarded
October 15, 2026
Identifier
RFP-2645-27
The University of New Mexico selected Jaynes Corporation for CMAR services for the Phase 1 University Stadium Improvements project. The selection committee identified Jaynes as the most advantageous respondent, citing its relevant project experience, staffing continuity, phased cost governance, and strategies for managing project risks. The source states Jaynes's total fee as $2,225,406.
Description
Construction Manager at Risk services for Phase 1 improvements to University Stadium, including concourse widening, restroom and concessions improvements, entry and circulation upgrades, accessibility and life-safety work, and phased construction to maintain stadium operations.