Loudoun County awarded purchase order 217866 to TIMMONS GROUP for services related to the River Bend Stream Restoration project. The PO lists five line items, each with quantity 1: River Bend Stream Restoration, Protocol 1 ($7,063.10); post-construction services after planting, project management ($7,063.10); post-construction Year 2 project manager services (18 hours; $7,063.10); post-construction Year 3 project manager services (18 hours; $7,063.10); and mileage for four visits at $166.25 per visit ($665.00). The award amount is $28,917.40. The Year 2 and Year 3 descriptions indicate services spanning multiple project years; no contract dates or specific contract requirements are provided.